Nevada Copper unveils restart and financing plan for Pumpkin Hollow

Components of the current work program include completing a second dike crossing during the third quarter and the final dyke crossing by the end of the year, starting to stope the higher grade East North mining zone in the second quarter of 2023, and restarting the mill in the third quarter of next year. 

If all goes to plan, Nevada Copper says, underground production will ramp up to hoisting rates of about 3,000 tons per day in the third quarter of 2023 and increase to 5,000 tons per day in the fourth quarter of the year. 

The restart will also involve changes to the company’s arrangements with the underground mining contractor to improve performance and ultimately to transition some mining activities to Nevada Copper itself. 

Under the terms of its financing package, Nevada Copper has agreements with its senior lender KfW IPEX-Bank (KfW); its working capital provider Concord Resources Ltd.; its largest shareholder, Pala Investments, and another shareholder Mercuria Energy; and Triple Flag Precious Metals (TSX: TFPM), its stream and royalty partner. 

Breaking the $93 million financing down into its parts, Pala and Mercuria will each pony up $20 million in exchange for common shares of the company and KfW will amend its senior credit facility to provide for a new tranche of up to $25 million, of which Pala, Mercuria and Triple Flag would commit the first $15 million as a backstop. 

Triple Flag will increase its existing net smelter returns royalty on the company’s open pit project development from 0.7% to 2% for a purchase price of $26.2 million (subject to a full buyback of the increased royalty percentage.) Triple Flag would also accelerate the $3.8 million remaining to be funded under Nevada Copper’s existing metals purchase and sale agreement.

Finally, KfW would defer three interest payments under its facility and Concord would defer interest and principal payments under its working capital facility. 

Under the agreement, Triple Flag and Mercuria will each have the right to nominate a director and a representative on the board’s technical committee. 

Challenging ramp-up

“The Pumpkin Hollow underground mine has been challenged with its ramp-up, and with the proposed financing package, we are hopeful the operation will be able to deliver into its designed potential,” mining analyst Rene Cartier, who covers Triple Flag for BMO, commented in a research note to clients. “We have moderated our near-term production expectations for the underground mine, and slightly pushed out development of the open pit.

“While some investors [in Triple Flag] may not view the increased exposure in Pumpkin Hollow favourably, this may be offset by turnaround prospects. However, given the existing open-pit encumbrance, and the transaction structure, we wouldn’t be surprised to see a buyback exercised,” Cartier added. 

The Pumpkin Hollow underground mine, and its open pit development project (which it is advancing through a prefeasibility study update), are about 13 km southeast of Yerington, and about a one and a half-hour drive southeast of Reno.

This post has been syndicated from a third-party source. View the original article here.